Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wp-embed-facebook domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home3/hipvacat/public_html/abdul2-rosslynredux-com/wp-includes/functions.php on line 6121

Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the wp-last-modified-info domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home3/hipvacat/public_html/abdul2-rosslynredux-com/wp-includes/functions.php on line 6121
Marvin Windows – Rosslyn Redux

Tag: Marvin Windows

  • Elevation Headway

    Elevation Headway

    It was a super Saturday for Rosslyn’s icehouse rehab. Several concurrent projects underway, but the most notable progress was the interior east elevation (in the loft) and the exterior west elevation. I’ll try to get out of the way and let the photos do the talking.

    Icehouse West Elevation Clapboard Complete (Photo: Geo Davis)
    Icehouse West Elevation Clapboard Complete (Photo: Geo Davis)

    The photo above is taken from the northwest of the barns, looking southwest toward the icehouse and carriage barn. Note that the clapboard installation is now complete on the west elevation of the icehouse. Congratulations to Supi and Calvin for crossing the west elevation and moving on to the east elevation.

    West Elevation Clapboard Installation Complete (Photo: Geo Davis)
    West Elevation Clapboard Installation Complete (Photo: Geo Davis)

    We’re still a couple of months shy of receiving our Marvin window delivery. It’s been a long, slow, process that started last August. But we’re more and more optimistic that we’ll be on target — or possibly even slightly ahead of schedule — when the windows arrive. For now you just have to imagine glass windows and doors and all of the polygons displaying ZIP System panels

    Can you picture what does façade will look like early this summer? We can’t wait!

    Loft East Elevation T&G Finished (Photo: Geo Davis)
    Loft East Elevation T&G Finished (Photo: Geo Davis)

    The photograph above shows the east elevation inside the loft shortly after the tongue and groove nickel gap installation was complete. Matt started it yesterday, and he wrapped it up with Jarrett today.

    Matt and Jarret Finished Loft Wall (Photo: R.P. Murphy)
    Matt and Jarret Finished Loft Wall (Photo: R.P. Murphy)

    What a day!