  • Cabinetry in Icehouse Loft

    Cabinetry in Icehouse Loft

    For such a nanoscopic space, it’s a little uncanny how much complex finish carpentry and how much cabinetry have been part of this final stretch in the icehouse rehab. Actually… it’s precisely *BECAUSE* of the nanoscopic proportions that we’ve emphasized builtins and detailed finish work. And degree-by-degree we’re measuring progress toward completion. Even the cabinetry in icehouse loft is beginning to take shape.

    An endoskeleton for the soon-to-be loft shelving has begun to take shape. Shop-built carcasses fabricated by Bernie Liberty have been delivered and installation has begun. Lining the north and south knee walls, these reading repositories will soon be lined with bound words… (Source: Loft Shelving)

    Cabinetry in Icehouse Loft (Photo: R.P. Murphy)
    Cabinetry in Icehouse Loft (Photo: R.P. Murphy)

    I accompanied my April 25, 2023 update with a haiku — a loft shelving haiku, of course, — brimming with bookish confidence. Bookshelf confidence, at least. I acknowledged my exuberance at the time.

    A little forward leaning, I suppose. Aspirational. Projecting, courtesy of my imagination, a few weeks forward… (Source: Loft Shelving)

    A few weeks forward?!?!

    “Piece of pie,” the carpenter responded in January when we discussed the icehouse loft cabinetry. He estimated “a couple of weeks” to fabricate and install the cabinets. My optimistic update (referenced above) was posted three months later when some carcasses had been delivered, and the first units were installed. Hhhmmm… Almost two months after that the face frame is joining the ensemble. Hurrah!

    Cabinetry in Icehouse Loft (Photo: R.P. Murphy)
    Cabinetry in Icehouse Loft (Photo: R.P. Murphy)

    I frequently remind Carley that anticipation is half the pleasure. She remains unconvinced, but lately I’ve been reminding myself that this isn’t just a patience mantra. There’s more than a kernel of truth in it. An aphoristic cousin to “distance makes the heart grow fonder”, perhaps?

    However we account for it, I’m relieved and more than a little thrilled to see my loft cabinetry coming together. Since this space will be my study, the lofty locus of my productivity, I have a vested interest in the timely and reliable execution of this builtin storage. A tidy workspace is a productive workspace! Heck, I’m overflowing with aphorisms today. And even an autogamous poem…

    Study & Studio Haiku

    Lo lofty locus,
    penning’s, typing’s, doodling’s
    manufactory.

    Speaking of anticipation, years of hope and expectation have fertilized the vision for my study-studio in the icehouse loft. A picture perfect panacea! And yet, I recognize the zealous overreach, understand that degrees of recalibration may be necessary. Soon.

    Loft Cabinetry

    With luck I’ll follow this post soon with a celebratory bookend to this project. Perhaps “a couple of weeks” will have extended into a couple of seasons, but I’ll be able to migrate my books and files and fountain pens and miscellaneous mementos into their new shelves and cabinets. I’ll be able to position my desk beneath the east side gable window and occupy the chair with a view for productive mornings in my loft. Ah, Elysium.

    My mind meanders, doubling back on an exchange with Pam this past winter.

    Geo: Builtins will combine open shelving (note dimension changes per our meeting) and cabinet doors (paint grade shaker style with flat panel and no panel molding) concealing deep cabinet storage. Please review plans and help me determine whether or not we can/should fabricate in-house or subcontract to a cabinetry shop. (Note: I’m hoping to evaluate whether or not our team is well suited to undertaking this mostly shop-work carpentry, and whether or not it is the most pragmatic use of our resources.

    Pam: Builtins have been snapped out. I have a cabinet maker stopping in tomorrow to see the scope of work and discuss his availability.

    Willing forward motion — cabinetry installation, final painting, hardware, and… migrating from the house to the icehouse — in the coming days.

  • Icehouse Loft Flooring Update

    Icehouse Loft Flooring Update

    Much of the current and upcoming stage in Rosslyn’s icehouse rehab involves covering, cladding, and closing in: clapboard siding, T&G nickel gap paneling, upcycled garapa paneling, and plenty of hardwood flooring. Today I’d like to get you up-to-date on the loft flooring.

    Loft Flooring Update (R.P. Murphy)
    Loft Flooring Update (R.P. Murphy)

    We’ve installed beech flooring that remained from the first floor reflooring (entrance hallway, living room, parlor, and kitchen) completed in 2007-8. Stored in the icehouse for the last decade and a half with plenty of additional surplus building materials, this handsome hardwood — originally selected for its local origins, pale color, and character-rich grain — has been repurposed as our new loft flooring.

    But, as often, I’m getting in front of myself. Before installation came acclimatization…

    Loft Flooring Update (R.P. Murphy)
    Loft Flooring Update (R.P. Murphy)

    Acclimating Beech Flooring

    A few weeks ago Tony and Peter relocated the beech hardwood flooring from one of the storage containers to the icehouse loft area where it was stacked and stickered strategically to maximize through-flow of warm, dry air. Frequent metering enabled us to track the moisture content of the flooring as it stabilized.

    Within a couple of weeks the temporary improvements to temperature and humidity control in the icehouse implemented Peter and Eric proved their value. The beech was ready to be installed.

    Loft Flooring Update (R.P. Murphy)
    Loft Flooring Update (R.P. Murphy)

    Loft Flooring Installation

    The beech was oriented perpendicular to the loft floor joists, starting at the east edge of the loft where we temporarily attached spacers (retainers for railing bottoms and the top stairway tread) to accurately determine the flooring’s start point. Beginning on this side enabled us to minimize the likelihood of a visible “pie wedge” given less than perfect geometry of our 130+ year old building.

    Prior to working west from the loft overhang, yes team marked out locations for future cabinets that will be fabricated and installed along the north and south knee walls. Because we were using remnant flooring (think limited quantity) we needed to prioritize the area of the floor that would be visible once the cabinetry was in place. We ran the flooring “ragged” under the cabinets — underlaying the figure cabinets without extending all of the way to the wall, allowing us to ensure sufficient material for the exposed area of the floor.

    Especial attention was paid to sequencing beech boards in a visually attractive progression, board-to-board, ensuring that the color and character variations would enhance the cohesive integration across entire floor.

    Another less visible but important detail: integrating the top stair tread. Peter shaped a beech slab to frame the flooring at the top of the staircase, routering in a tongue for the 90° conjunction between flooring and beech stair tread. This has added a little extra time, but it ensures a more stable joint in a high traffic, high visibility transition.

    Now that the loft flooring is installed, it’s time for sanding and sealing. I’ll post an update soon!