Tag: Energy Efficiency

  • Icehouse Insulation Installation Complete

    Icehouse Insulation Installation Complete

    Phew. With Rosslyn’s icehouse insulation installation complete we can collectively exhale, confident and warm. Today I’d like to offer huge holiday shoutout to Kevin and Joe from Adirondack Spray Foam for wrapping up 2022 with the winter-proof armor we need to keep the icehouse project going fullbore over the coming months. Bravo!

    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)
    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)

    Some progress is pretty. Framing new window aprtures, for example. And some progress is practical. Installing helical piers, for example. Insulation installation is *indisputably* in this second category. And yet, aaahhh… What a relief to have the first phase of insulation complete! (Source: 1st Floor Insulation Installation and Subfloor)

    Those were my thoughts a couple of weeks ago when we started installing spray foam insulation. If phase one was a relief, completion is resoundingly reassuring, like a bear hug from the universe. Things are going to be alright. Winter will huff and puff, maybe even blast us with blizzards and deep freezes. But we’re cocooned snuggly inside a protective force field.

    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)
    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)

    And combine the insurance of a thoroughly spray foamed building with the just completed ZIP System insulated sheathing swaddling is from the outside in? Aaahhh… It’s warming to just think about it. Ongoing rehab can continue afoot despite the taunts of our Adirondack Coast winter.

    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)
    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)

    As I’ve explained previously, we installed 1-1/2” structural insulated panels on the exterior which provides R-6. The 3” of spray foam inside the walls adds another R-21, and there’s a bonus between the two synthetic insulation barriers. When the size house was built in the late 1800s, they filled the interior 2 x 6 walls with wood shavings for insulation. Although we removed all of that in 2006 while remediating rot, the exterior of the framing was sheathed in two laters of T&G separated by about an inch baffled with shredded newsprint enveloped in tarpaper. So these walls should now do a remarkable job of keeping winter cold out, and summer cool in.

    What about the roof?

    Adirondack Spray Foam installed 7” on insulation between the rafters which will amount to an R-49 thermal barrier sandwiched between the ceiling and the roof.

    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)
    Installing Spray Foam in Icehouse Ceiling (Photo: R.P. Murphy)

    A decade and a half ago we wrestled with the best way to balance insulate Rosslyn. Ultimately, we concluded that our historic rehabilitation needed to balance heritage and environmental responsibility. Although we also use recycled denim insulation and mineral wool when appropriate, we’ve come to trust the energy efficiency of spray foam.

    Insulation Installation Complete in Time for Winter

    And then it was done. With our insulation installation complete, we can rest a little easier. January will inevitably plunge us into all manner of meteorological challenges, but we’re now in a much better position to power forward.

    Insulation Installation Completed by Adirondack Spray Foam (Photo: R.P. Murphy)
    Insulation Installation Completed by Adirondack Spray Foam (Photo: R.P. Murphy)

    Although blue green doesn’t exactly *look* warm, the icehouse now can be warmed with a space heater. We’ll see if reality meets expectation this week.

    Insulation Installation Completed by Adirondack Spray Foam (Photo: R.P. Murphy)
    Insulation Installation Completed by Adirondack Spray Foam (Photo: R.P. Murphy)

    In addition to wall-to-wall insulation these last two photos capture the post cleanup tidiness. It’s the perfect tabula rasa to start framing this week.

    Spray Foam Insulation Mashup

    Let’s curtain call this post with an almost meditative mashup of the last lap of spray foam installation.

    https://www.instagram.com/reel/Cmp97yYB_hi/?igshid=YmMyMTA2M2Y=

    Thanks, Kevin and Joe.

  • Icehouse Rehab 8: 1st Floor Insulation Installation and Subfloor

    Icehouse Rehab 8: 1st Floor Insulation Installation and Subfloor

    Icehouse Insulation Installation Begins (Photo: R.P. Murphy)
    Icehouse Insulation Installation Begins (Photo: R.P. Murphy)

    Some progress is pretty. Framing new window aprtures, for example. And some progress is practical. Installing helical piers, for example. Insulation installation is *indisputably* in this second category. And yet, aaahhh… What a relief to have the first phase of insulation complete!

    Icehouse Insulation Installation Progress (Photo: R.P. Murphy)
    Icehouse Insulation Installation Progress (Photo: R.P. Murphy)

    The crawlspace beneath the main floor is now isolated from what will become the first floor by a whole lot of insulation. If you look closely in the photo above you’ll see small furring strips installed at the bottom of the floor joist. We installed 2″ rigid foam insulation board on top of these and then sprayed in XXX of closed cell foam insulation.

    Icehouse Subfloor Installation Begins (Photo: R.P. Murphy)
    Icehouse Subfloor Installation Begins (Photo: R.P. Murphy)

    Because this is an historic rehabilitation project, preserving the original stone foundation was critical. Successfully pinning the new foundation to the old (ensuring structural integrity for new construction) prevented us from isolating the thermal bridge (old stone foundation plus new concrete foundation and slap). So we framed in a gap around the entire perimeter of the building that allowed us to create a spray foam insulation barrier, minimizing the transfer of cold exterior temperatures during the wintertime. We also foamed the entire curb inside the crawlspace, to further isolate the thermal bridge and reduce interior and exterior temperature exchange. The photo above shows the framing gap around the perimeter, filled with foam insulation.

    After Insulation Installation…

    Once the spray foam insulation installation was complete, it was time for a subloor.

    Icehouse Subfloor Installation Progress (Photo: R.P. Murphy)
    Icehouse Subfloor Installation Progress (Photo: R.P. Murphy)

    Supi guided this important step forward so that we can set up staging to frame the west and east gable end windows.

    Icehouse Subfloor Installation Almost Complete (Photo: R.P. Murphy)
    Icehouse Subfloor Installation Almost Complete (Photo: R.P. Murphy)

    In this final photo you can see the last narrow strips of subfloor are about to be installed. Not bad for a day’s work!

    Insulation Installation and Subfloor Mashup

    Haven’t done an exceptionally thoughtful writeup with this post, so perhaps remixing into a begin-to-end recap of the first phase insulation installation and subfloor installation will fill in some gaps. Hope so!

    https://www.instagram.com/reel/Cl_Sk_Gg7Xo/

    Thanks to Kevin’s spray foam insulation team and everyone else who helped us to reach this next significant milestone. Just imagine once the walls and roof are insulation and the ZIP System panels are installed around the interior exterior envelope. Might start to warm up a little…